The plastic lane delineators creating chicanes to slow traffic on Port Moody’s Moray Street could soon be gone.
In their place, new curb bulges will be built at Pinda Drive and Brookmount Avenue, along with new lane markings and crosswalks. But a planned bike lane on the east side of Moray Street will have to wait.
Tuesday, May 20, Port Moody council’s initiatives and planning committee will consider spending an additional $353,000 to construct the new, permanent elements. That’s on top of the previous budget of $795,000 that had been approved in 2022.
Since then, though, construction costs have risen, additional design work was required and $187,000 will be allocated to a new multi-use path on the west side of Moray, resulting in a total budget of $1.248 million, said a staff report; $100,000 of that will be covered by the city’s street lighting relocation program, and another $155,000 will come from a TransLink grant.
A pilot project to slow traffic using Moray Street that was implemented in the summer of 2022 resulted in a 5-6 km/h reduction of speeds on the busy connector route to Coquitlam, according to the report.
But some residents said the temporary measures, that included the plastic lane delineators, new markings on the pavement to configure curb bulges at intersections and a temporary sidewalk on Moray’s west side, actually made the situation worse.
“It may have calmed traffic on the east side, but they’re going faster on the west side,” said one resident prior to a meeting last June when council decided the traffic calming measures should be made permanent.
Subsequent feedback from residents following a public information session earlier this year revealed further concerns like the loss of several on-street parking spots, worries about pedestrian safety from cyclists speeding down a northbound bike lane and turns lanes at the St. Johns Street intersection too short to accommodate the volume of vehicles.
As a result, said the report, further refinements have been made to the permanent calming plan, including:
- the addition of eight new on-street parking spots on the east side of Moray, between Brookmount Avenue and Portview Place
- the removal of the northbound cycling lane on the east side of Moray; instead, cyclists heading down the hill will be directed to use Brookmount Avenue and Clearview Drive while staff consider further options
- additional curb bulges to be built at the intersection of Moray and Brookmount, as well as a new marked crosswalk on the north leg
- adjustments to the lane geometry at Moray and St. Johns to extend the turning lanes so they can accommodate more vehicles
The report said the permanent changes should be in place by the end of the year.